Anthropic Invests $3.4 Billion in Gas Turbines

Faced with the growing difficulty of obtaining electricity for AI, Anthropic is investing $3.4 billion in gas generators capable of providing up to 1.7 GW. This decision comes as supply lead times are extending and gas prices could rise significantly by the end of the decade.
Lead Times Extending to the 2030s and Assumed Price Risks
The lead times for obtaining natural gas turbines are now extending into the early 2030s, while connecting to the electrical grid can take just as long. Dependence on natural gas also exposes operators of large data centers to price volatility. An analyst predicts that gas prices could more than triple in some markets by the end of the decade. If this scenario materializes, Anthropic could face challenges with this investment.
Direct Purchase of Caterpillar Generators After a OnePWR Option
Anthropic is dedicating $3.4 billion to the purchase of Caterpillar generators, initially ordered by OnePWR. These units can provide up to 1.7 gigawatts of electricity. OnePWR had placed the order a few years ago but was unable to secure the necessary funding. Anthropic had initially considered buying the turbines from OnePWR before turning directly to Caterpillar to finalize the acquisition.
Le brief IA que les pros lisent chaque soir
Les 7 actus IA du jour, décryptées en 5 min. Gratuit.
Inclus dès l'inscription : notre sélection des meilleurs guides & comparatifs IA.
Choisissez votre rythme
Gratuit · Pas de spam · Désabonnement en 1 clic
Massive Computing Rental and Planned IPO
Until now, Anthropic has favored renting infrastructure over purchasing. The company plans to go public this year. In an S-1 filing submitted in May, it indicated that it is paying $1.25 billion per month to xAI, a subsidiary of SpaceX, until May 2029 for access to computing power, and plans to enter into other similar contracts. The purchase of gas turbines thus adds to these already significant rental commitments.
Cloud Giants Betting on Gas and Reviving Fracking
AI companies are increasingly purchasing equipment that runs on natural gas. Google, Amazon, Microsoft, and Meta have announced plans for gas power plants to supply their on-site data centers, rather than relying on the public grid. This trend is contributing to a resurgence in hydraulic fracturing. If these projects come to fruition, American data centers could consume more natural gas by 2035 than Germany and Japan combined. This shift responds to a particularly strong demand for electricity deemed necessary for AI.