Key Takeaways
1RETN reports an increase of about 50% in the prices of optical equipment since the beginning of 2026.
2Lead times are reaching 12 to 15 months, with some orders extending up to 18 months, according to RETN.
3Outside of established hubs, RETN recommends partnering with operators two to five years before opening.
Why it matters : remote sites may lack fiber to connect to customers and other data centers.

RETN reports delays of up to 18 months for certain optical network equipment, with prices having increased by approximately 50% since the beginning of 2026. The operator attributes these pressures primarily to demand related to AI, as the need for redundant connections rises.

Customers Request Four Distinct Paths

According to RETN, customers who previously accepted two paths for their long-distance connections are now demanding four or even more. The operator considers this diversity essential to ensure that a single incident does not disrupt critical services. It is crucial that the connections do not share common conduits or cable routes exposed to the same physical risks.

A diversified circuit could cost €1,800 per month, or $1,975, compared to €600, or $658, for a non-diversified circuit. However, a failure could end up costing much more.

Isolated Sites Must Anticipate Their Connections

RETN observes a shift of AI centers to less populated areas, where suitable land, water, and energy can be more accessible. Hyperscalers are particularly building in Nordic countries: land is affordable, temperatures are cooler, and renewable resources are abundant. However, isolated sites may lack the necessary fiber connections to reach their customers or other data centers.

The evening letterFree · 7 pm

The AI brief the pros read every evening

The 7 best AI stories, the essentials in 5 min. Free.

Included when you join: our pick of the best AI guides & comparisons.

Choose your rhythm

Free · No spam · Unsubscribe in 1 click

Near cities, developers often take on the connection costs for a few percentage points more of the overall budget. For long distances, the expense is less easily justified, and operators hesitate to deploy a link intended for a single site. Nevertheless, RETN reports that a major cloud provider is considering converting a decommissioned factory in Central Europe into a large server center in a region poorly equipped with fiber.

For projects outside established hubs, RETN recommends involving operators two to five years before opening. The preparation for the connection should accompany the energy supply and construction planning, rather than occurring just before commissioning.

Equipment Faces Multiple Supply Pressures

Typical lead times have increased from three months to a range of 12 to 15 months, according to RETN. The situation is comparable, if not more challenging, than during the pandemic when chip shortages prevented suppliers from fulfilling orders. Demand now exceeds supply due to the expansion of AI: network and telecommunications operators and data centers are competing for the same components.

The sudden demands from hyperscalers and AI campuses are compounded by shortages of raw materials and skilled personnel, energy limitations, geopolitical tensions, and logistical obstacles. RETN also acknowledges that many operators have postponed their upgrades to save costs. These upgrades are now unavoidable, as supply conditions remain unfavorable.