Oracle Claims to Have Funded Its Entire Contract with OpenAI

Creative AI·Tom Levy·

Oracle Claims to Have Funded Its Entire Contract with OpenAI

Oracle Claims to Have Funded Its Entire Contract with OpenAI
Key Takeaways
1Oracle claims to have all the necessary funding for its contract with OpenAI.
2The group aims for over $30 billion in free cash flow for the fiscal year 2029.
3Oracle and OpenAI are planning an additional 4.5 gigawatts in the United States, according to a source.
Why it matters : Oracle asserts that the execution of its contract with OpenAI does not depend on further discussions with its suppliers.

Oracle claims to have secured all the necessary funds to fulfill its infrastructure contract with OpenAI, following a $20 billion debt and equity operation earlier this month. In a message posted on X on Friday, the company preemptively dismissed any information that would contest this financial coverage.

Oracle Aims for Positive Cash Flow by 2028

Oracle's spending on its data centers already exceeds its quarterly revenue. Investors are questioning the capital needed for this expansion into AI as well as the group's exposure to OpenAI. Earlier this month, Microsoft undertook to revise down its agreement for AI computing capacity leasing from Oracle.

For the second half of fiscal year 2028, Oracle continues to forecast positive free cash flow. For fiscal year 2029, the group aims to generate over $30 billion in free cash flow and anticipates self-funding its growth starting in that fiscal year. In a second message, Oracle reminded that its statements are forward-looking: significant risks and uncertainties could lead to different outcomes.

La lettre du soirGratuit · 19 h

Le brief IA que les pros lisent chaque soir

Les 7 actus IA du jour, décryptées en 5 min. Gratuit.

Inclus dès l'inscription : notre sélection des meilleurs guides & comparatifs IA.

Choisissez votre rythme

Gratuit · Pas de spam · Désabonnement en 1 clic

Oracle Considers Discussions with Suppliers Optional

For Oracle, the resources presented during its investor day are now available, including funding from suppliers. The company describes any potential additional private discussions with them as optional opportunities, which would not depend on the execution of its commitments to OpenAI. It also positions itself as the first fully funded hyperscaler for this investment cycle.

Oracle does not specify which media reports its clarification intends to contest. Its statement was released at 4:01 PM in New York, one minute after U.S. markets closed. The Oracle stock then gained up to 3.3% in after-hours trading.

Abilene and Shackelford Campuses Progressing

In the United States, Oracle and OpenAI plan to add 4.5 gigawatts of capacity to the first Stargate site in Abilene. Oracle describes a rapid progression in their partnership and presents the Abilene campus in Texas as nearly completed. According to the group, this site has hosted the training of OpenAI's model designated as Astra-6 in its message.

The next campus, located in Shackelford County, Texas, is set to reach gigawatt scale. Oracle claims to have obtained all the necessary permits for this site. The company expects Nvidia Vera Rubin racks in its data centers over the coming weeks.